In 2004, Sithe Global Power, LLC. proposed construction of the Desert Rock Energy Facility, a new 1500 megawatt coal-fired power plant on the Navajo Nation tribal reservation, approximately 25 miles southwest of Farmington, New Mexico. In consideration of over 1,000 oral and written comments received during an extended public comment period in 2006, EPA made a final decision on July 31, 2008 to issue a Prevention of Significant Deterioration (PSD) permit for this facility. The administrative record for the initial permit is available through regulations.gov. See docket EPA-R09-OAR-2007-1110.Exiting EPA (disclaimer)

Following EPA’s final permit decision, several parties appealed that decision to the Agency’s Environmental Appeals Board (EAB). The Desert Rock Energy Company can not begin construction of the facility until this appeal process is completed. Documents filed in the appeal are available in the Desert Rock Energy Company, LLC docket on the EAB’s website.

On January 7, 2009 EPA notified the EAB that it was withdrawing a portion of our permitting decision for further consideration. Following the withdrawal EPA prepared an addendum to the statement of basis for the permit which addresses the issue of whether a final PSD permit for the Desert Rock Energy Company should contain emissions limitations for carbon dioxide. EPA requested public comments on this addendum from January 22, 2009 through March 25, 2009. The administrative record for the addendum to the statement of basis is available through regulations.gov. See docket EPA-R09-OAR-2009-0259. Exiting EPA (disclaimer)

http://www.epa.gov/region09/air/permit/desert-rock/index.html

Advertisements

2 Responses

  1. […] Prevention of Significant Deterioration (PSD) Permit for the …Get Social. Bookmark Nuclear and Indigenous Items of Interest … In 2004, Sithe Global Power, LLC. proposed construction of the Desert Rock Energy Facility, a new 1500 megawatt coal-fired power plant on the Navajo Nation tribal reservation , approximately 25 miles southwest of Farmington, New Mexico. In consideration of over 1000 oral and written comments received during an extended public comment period in 2006, EPA made a final decision on July 31, 2008 to issue a … […]

  2. […] Prevention of Significant Deterioration PSD Permit for the Posted by root 16 hours ago (https://gregornot.wordpress.com) Apr 29 2009 the desert rock energy company can not begin construction of the facility until this oral and written comments received during an extended public comment period in 2006 powered by weread middot blog at wordpress com Discuss  |  Bury |  News | prevention of significant deterioration psd permit for the […]

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: