Uranium storehouse not ready to load yet

Please read article, cited after the quote. Articles open in a new window.

OAK RIDGE – Construction of the government’s new storehouse for bomb-grade uranium is complete, but no uranium will be loaded into the fortress-like facility for more than a year.

A lot of testing and training will take place in the months ahead, and that will be followed by a series of readiness reviews to actually certify the high-security nuclear facility for use.

“We expect to receive authorization to begin loading the facility about March 2010,” Steven Wyatt, a federal spokesman at the Y-12 nuclear weapons plant, said in an e-mail response to questions.

http://www.knoxnews.com/news/2009/jan/02/uranium-storehouse-not-ready-to-load-yet/

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: